Project Consultants and Contractors

Sl. No.

Contract Title & Ref.

Contract Amount (incl. VAT, Tax, Import Duties) (BDT in Crore)

Contract Signing Date

Date of Commencement

Contract Completion Date

Remarks

01

Package -1:  Design and Build of Intake , Raw Water Pipeline and 500 MLD Water Treatment Plant at Gandharbpur under Dhaka Environmentally Sustainable Water Supply Project (DESWSP)”.

DBO package (D&B contract )no: ICB-01/ D&B/DESWSP/2014.

3006.043

O&M Cost: 104.0759

16.05.2018

13.05.2019

 

12.05.2023

Contract Revision Required.

02

Package -2:  Treated Water  pipeline under DESWSP ,DWASA

 (Contract no:ICB-3.0/TWP/DESWSP/2018)

777.400

06.05.2021

 

15.09.2021

14.09.2024

Work Ongoing.

03

Package-3.1: Distribution Reinforcement under ADB financed Dhaka Environmentally Sustainable Water Supply Project”.

 (Contract No:ICB-4.0(DRPL)/DESWSP/2018

589.319

09.09.2021

-

-

Contract Commencement Letter will be provided soon.

04

Package-3.2: Design and Construction of Feeder Line Inside Dhaka City under DESWSP, DWASA.

(Contract no:06/FL/DESWSP/2020

372.921

 

28.12.2022.

 

 

 

-

-

Contract Commencement Letter will be provided soon.

05

Package  ICB-02.7: Distribution network improvement [75mm-450mm Dia & (500 km in MODS zone-6 area)]

292.547

30.03.2015

02.07.2015

 

30.05.2021

Contract Revision Required.

06

Management, Design and supervision consultant (MDSC) for design review and supervision of construction for the design build operation (DBO) contract comprising River water intake ,Raw water pipeline and a 500MLD capacity water treatment plant (WTP),detailed design ,Supervision of construction works of two pipeline packages under DESWSP,DWASA.

155.034

30.03.2023

30.03.2016

31.01.2023

Contract Revision Required.

07

Management, Design and Supervision Consultant (MDSC)for design review and supervision of construction for the design build (DB) contract comprising River water intake , Raw water pipeline and a 500MLD capacity water treatment plant (WTP),Detailed Design ,Supervision of construction works of two pipeline packages(P2,P-3.1)and Design Review Supervision of feeder line package (P-3.2) Under DESWSP,DWASA.

127.269

31.03.2023

01.02.2023

31.10.2023

Ongoing.

08

NGO Service of “Resettlement Implementation  assistance for construction  Intake, Raw Water Transmission Line ,500 MLD Capacity Water Treatment Plant and Finished Water Line up to Baridhara Injection Point.”

 

11.849

29.05.2022

01.01.2022

30.03.2023