Sl. No. |
Contract Title & Ref. |
Contract Amount (incl. VAT, Tax, Import Duties) (BDT in Crore) |
Contract Signing Date |
Date of Commencement |
Contract Completion Date |
Remarks |
01 |
Package -1: Design and Build of Intake , Raw Water Pipeline and 500 MLD Water Treatment Plant at Gandharbpur under Dhaka Environmentally Sustainable Water Supply Project (DESWSP)”. DBO package (D&B contract )no: ICB-01/ D&B/DESWSP/2014. |
3006.043 O&M Cost: 104.0759 |
16.05.2018 |
13.05.2019
|
12.05.2023 |
Contract Revision Required. |
02 |
Package -2: Treated Water pipeline under DESWSP ,DWASA (Contract no:ICB-3.0/TWP/DESWSP/2018) |
777.400 |
06.05.2021
|
15.09.2021 |
14.09.2024 |
Work Ongoing. |
03 |
Package-3.1: Distribution Reinforcement under ADB financed Dhaka Environmentally Sustainable Water Supply Project”. (Contract No:ICB-4.0(DRPL)/DESWSP/2018 |
589.319 |
09.09.2021 |
- |
- |
Contract Commencement Letter will be provided soon. |
04 |
Package-3.2: Design and Construction of Feeder Line Inside Dhaka City under DESWSP, DWASA. (Contract no:06/FL/DESWSP/2020 |
372.921
|
28.12.2022.
|
- |
- |
Contract Commencement Letter will be provided soon. |
05 |
Package ICB-02.7: Distribution network improvement [75mm-450mm Dia & (500 km in MODS zone-6 area)] |
292.547 |
30.03.2015 |
02.07.2015
|
30.05.2021 |
Contract Revision Required. |
06 |
Management, Design and supervision consultant (MDSC) for design review and supervision of construction for the design build operation (DBO) contract comprising River water intake ,Raw water pipeline and a 500MLD capacity water treatment plant (WTP),detailed design ,Supervision of construction works of two pipeline packages under DESWSP,DWASA. |
155.034 |
30.03.2023 |
30.03.2016 |
31.01.2023 |
Contract Revision Required. |
07 |
Management, Design and Supervision Consultant (MDSC)for design review and supervision of construction for the design build (DB) contract comprising River water intake , Raw water pipeline and a 500MLD capacity water treatment plant (WTP),Detailed Design ,Supervision of construction works of two pipeline packages(P2,P-3.1)and Design Review Supervision of feeder line package (P-3.2) Under DESWSP,DWASA. |
127.269 |
31.03.2023 |
01.02.2023 |
31.10.2023 |
Ongoing. |
08 |
NGO Service of “Resettlement Implementation assistance for construction Intake, Raw Water Transmission Line ,500 MLD Capacity Water Treatment Plant and Finished Water Line up to Baridhara Injection Point.”
|
11.849 |
29.05.2022 |
01.01.2022 |
30.03.2023 |
|